With the floor, dwarf walls and upgrades in place we insulate the entire loft, cross batten and install stud walls for en-suites, second bedrooms or walk in wardrobes etc.

Once the loft is partitioned off into rooms the Velux and Dormer windows are install and the first fix plumbing and electrics are put into place.

At his stage we are ready to fit the new staircase so the ceiling is cut away and the staircase is formed and put into place. We then fit the hand rail and spindles to the new staircase and for any partition walling around the staircase.

We then plasterboard the new loft rooms and partitions and install doors, door casings, skirting board and architrave.

All the new rooms and surfaces are then plastered and the second fix electrics and plumbing and then installed.

The project is now complete and all the necessary arrangements will be made to have the scaffolding dismantled, skips remove and all debris cleared.